1. Current Location: Home >  NAS >  Synology upgrading to a new NAS doesn't require removing the old drive; the 206GB can be finished in two hours, so remember to add four things

Synology upgrading to a new NAS doesn't require removing the old drive; the 206GB can be finished in two hours, so remember to add four things

How to migrate data when upgrading to a new Synology NAS: Comparison between direct drive transfer and Migration Assistant network migration, plus four manual supplements after migration

My mom's Synology DS220j is an entry-level model from 2020. It uses Realtek's dual-core chips and 512MB of RAM, and running Rsync can fully load the CPU. Back then, treated it as a remote backup device, pulling a 206GB photo copy from my Feiniu every early morning. It has been doing this for over two years without ever making mistakes. What really made me decide to upgrade was that my mom's phone was almost full of 128GB and I wanted to install Synology Photos for automatic backup of phone photos—a 512MB memory, so don't make things difficult for her.

After returning home on the 19th day, I packed in my backpack a DS220+ (J4025 dual-core, 2GB RAM, much more decent than the old machine), plus two new 4TB Cool Wolf 1,100 yuan. This time, I didn't remove a single old listing; I took the path of network migration, which took two hours in total. Record the process and pitfalls for others who want to upgrade their phones for reference.

First, distinguish between two moving paths; don't jump right in and out

of the move

Synology upgrades to new machines—how will the data be passed? To put it bluntly, there are two paths. The first rule is Unplug and plug in the drive: Shut down the old machine, insert the hard drives one by one into the new machine in their original positions, and let it recognize them at power-on. This path is fast, but only if the old machine is no longer working or you're about to sell it, and the discs are still the same old ones, meaning you only changed the body but never the discs.

The second is the online migration I was doing this time. The official suite is called Migration Assistant, and in the Chinese interface, it's called Migration Assistant. The old machine was left untouched, and data was pulled over the network to the new machine's new hard drive. This applies to my situation: I want to replace the hard drive with a new one; the old machine can still boot and transition, but if the new machine has a problem, the old machine can instantly replace it. the 3-2-1 backup baseline has never been broken.

The When migrating , along' to , and
Comparison items: Unplugging drives directly into network migration (migration assistant):
Hard drives are reused with old drives; new machines paired with new drives
old machine must be able to shut down, shut down, and use while moving
with the system configuration and user driveselect 'Bring it
ensure the old machine is broken or will be discarded
you need to keep a backup plan

Of the three things I did before I started, I almost wasted one

First, align the DSM versions of both machines first. The official requirement is that the source machine starts at DSM 6.0, with recommended 6.2.2 or above, and the target machine must be no lower than the source machine. I directly upgraded both her old machine and my newly acquired DS220+ to the latest 7.2 version, so I wouldn't have to fight over the versions. As usual, take a snapshot before the upgrade.

Second, the new machine only does two things: install the system and build the storage pool. I plugged in two new 4TB Cool Wolf drives, set up the pool and storage space, and selected Btrfs for the file system—older machines already use Btrfs, so snapshot capabilities can't be lost when switching devices. Here's a pitfall that the official technical specifications clearly state, but I almost fell into: during migration, the data and system settings already on the target machine will be completely overwritten. In other words, on a new machine, all you can do is install the system and build the pool—don't add anything else. I was itching to set QuickConnect and time zone settings first, but luckily I held back. Even if I did, it was for nothing—the coverage was completely gone.

Third, export a backup configuration from the old machine. Control Panel, update and restore, configure backups, export the bin file and save it on my phone. This is a life-saving move—network migration doesn't involve data from old machines, but it's important to keep a backup before configuring the system. It's a habit I've been stingy with for three years.

The entire online migration process: two hours, and the old machine never stopped

The direction of this kit is the opposite of what many people think: it's installed on new machines, not on old ones. At first, I thought I had to go to the kit center for an old machine, but after searching for a long time, I couldn't find it. Later, I realized it after checking the official documentation. Step 3: Install Migration Assistant in the center of the new machine package, confirm the storage pool is created, and open the package.

Opening it is a wizard. First, select the source, enter the old machine's IP and administrator account password. After connecting, it will list the items you can transfer and check: shared folders with data, system configuration, users and user groups, and installed packages. I ticked them all. I casually checked the capacity—the target pool must be greater than or equal to the source pool, so I have 4T against 4T, which is safe.

Start the process, and the progress bar will start moving. 210GB or so, both machines were on my mom's restaurant table, running on gigabit intranet. The first hour was fast, but later the small files slowed down, taking just over two hours in total. During this time, the old machine stayed on standby, and my mom even glanced at the photos on her phone and wasn't affected. The official call this 'maximizing service availability during migration.' In plain terms, old machines are used while migrating, and after the migration starts, the newly generated data is recovered at the end.

After running the new machine and restarting, I was stunned for a few seconds when I logged in—the interface, username, shared folder, even the read-only account I set for her were all there, as if the old machine had been brought over as is. My mom installed Synology Photos on her Huawei phone, logged in with her old account, and the photo library went straight to view. she also enabled auto-backup of phone photos. 2GB RAM runs this without worry.

Moving isn't the end; four things need to be manually replaced

The migration assistant manages the stuff inside the machine; it doesn't handle relationships outside the machine. After moving, I checked each one by one, and there were four things I had to do myself.

Why ? The , all the old . The own the with your own eyes. You have to
do you need to add something
other side of the synchronization task. My Feiniu's rsync is pointing to an old machine, so I changed the push target to the new machine's IP and restarted the check
checking both the phone and computer clientThe address changed, and the app re-addedDS finder and Photos files to the new machine
Docker container and the authorized package container didn't have to crawl up on theirto check the status. The monitoring suite authorization needed to reactivate
timing and power scheduleWhether the quest is present or not depends on seeing itredo the clock-on/off rhythm at midnight

The head is the most important. The official documentation specifically mentions: if the source machine is one end of the shared folder synchronization, after migration, the synchronization relationship must be reconnected on the target machine. My scenario is Feiniu pushing photo copies to her home every early morning. I change the other side's IP address, check the logs the next day, the alert push quietly and quietly, and the new volume is being sold normally. Only then can I finally relax.

I actually checked the last thing: The power plan for booting at 3:20 AM and shutting down at 4:30 AM was still there, but I checked the two scripts in the task schedule one by one and checked the paths and parameters. When it comes to changing phones, it's better to take a second look than bet on its foolproof quality.

Old machines, don't rush to make a move

The new machine ran steadily for a week before I switched to the old one. It now has a new role: after clearing redundancy, it is used as local cold reserve downgrade, since two 4T units can still fight. If you plan to sell second-hand, remember to clean the hard drive data before shipping. Quick formatting means no deletion is allowed. For mechanical drives, just write zero. I did this once for my cousin'>s old drive

Here's a little reminder during the transition period: during the days when both machines are online simultaneously, make sure not to have overlapping IPs. For my new machine, I first use a temporary IP and only change it to the old machine's original address after confirming the old machine is offline, so I won't have to update the push tasks at home again.

What circumstances are worth taking this path

? In short, it comes down to

one thing: old machines can still boot, you want to replace the entire unit at once, or if you don't want to cut off service during the move, move via the internet; If the old machine is already dead or about to be sold out, there's no choice—just pull out the drive and plug it in. This time, I moved the 206GB in two hours, and the user permissions weren't reconfigured at all. My mom didn't feel the switch, so the 2,500 was worth it.

Here's the order to wrap up: version alignment, new consoles build pools without any other setups, old consoles backed up and installed, then kits installed and migrated; After migration, first add the synchronous end-to-end, then the client, and pass containers and scheduled tasks one by one; Leave the old machine for a week for observation, then clean it before making a move. If you follow this path, you can sleep soundly on the day you change phones.

Read More


Copyright Notice Scan to read on mobile
All Rights Reserved: 《SHUNOT》 => 《Synology upgrading to a new NAS doesn't require removing the old drive; the 206GB can be finished in two hours, so remember to add four things》
Article URL: https://www.shunot.com/en/nas/1198.html
Unless otherwise stated, all articles are original by 《SHUNOT》. Reposting is welcome! Please indicate the original URL when reposting, thank you.

Contact Us

Online Consultation: Click here to send me a message

WeChat ID: master_135

Scan to follow